How are planned revenue and planned cost calculated?
Planned revenue and planned cost are the forward-looking versions of actuals, built from Allocations (or budgets for fixed price projects) and Planned expenses rather than tracked work. Like actuals, each combines a work stream and an expense stream, with planned revenue branching by billing type.
Written By Lauri Eurén
Last updated 6 days ago
Planned revenue and planned cost are the forward-looking versions of revenue and cost. They are what you expect a project to earn and to cost, built from the plan (Allocations and Planned expenses) rather than from tracked work.
Like the actual figures, each combines two streams: work and expenses. Planned revenue also branches by billing type.
Planned cost = planned work cost + planned expense cost.
Work cost = allocation % × cost rate × working hours, summed across the allocated dates.
Expense cost = the cost of each Planned expense, billable or not.
This is the same on every billing type.
Planned revenue = planned work revenue + billable Planned-expense revenue, where work revenue depends on the billing type:
Time-and-materials: allocation % × billing rate × working hours, summed across the dates, plus the billed amount of each billable Planned expense.
Capped time-and-materials: the same, up to the Budget's cap. The cap is an amount or a number of hours.
Fixed-price: the Budget, distributed across time by the revenue recognition method — not the Allocations. Allocations still drive planned cost (and, for the weighted method, shape how the budget spreads), but they don't set planned revenue. Billable Planned expenses recognize through the same method.
Retainer: the fee (or budget) of each retainer period, spread evenly across the period's weekdays, plus overage for planned hours past the period's included hours, at the billing rate. Billable Planned expenses add their billed amount on top of the fee.
Non-billable: zero.
Both confirmed and tentative Allocations count wherever Allocations drive the figure: all planned cost, and planned revenue for time-and-materials. So tentative work is part of the plan. Reports keep the two distinct, so you can read committed (confirmed) work separately from tentative, potential work rather than seeing only a combined total.
What working hours go into the formula
The hours in each day's planned figure are the Person's working hours for that day, adjusted by Operating's working-hours rules:
Days without working hours, and dates outside the Person's employment dates: zero. Working hours are set per weekday, so a Saturday or Sunday has hours only when the Person's working hours include it.
Confirmed Time off: a confirmed full-day Time off leaves zero. A partial Time off first fills the part of the day that the Person's work leaves free, and only the rest reduces the work. On an 8-hour day with a confirmed 50% Time off, a Person allocated 100% gets 4 planned hours, and a Person allocated 50% also keeps 4 planned hours. Tentative Time off does not reduce the hours.
On a public holiday: reduced by the holiday's percentage. A 50% holiday gives half a day.
Otherwise: the Person's individual working hours, or the Site's hours when no individual hours are set.
So planned cost drops automatically across holidays and leave on any project, without anyone editing the Allocation — fewer working hours means less cost. Planned revenue drops the same way for time-and-materials and capped time-and-materials, where revenue follows the hours. Fixed-price revenue does not: it comes from the Budget and is recognized on its own schedule, so it doesn't move with holidays or leave.
A retainer's fee doesn't move with holidays or leave either; only its planned overage does.
Worked example (time-and-materials)
Take a Person allocated 50% for a week. Five working days × 8 hours is 40 full-time hours, so 20 allocated hours. The billing rate is $150/hour and the cost rate is $90/hour. There is also a $200 billable Planned expense billed to the client at $250:
Planned work revenue = 150 × 20 = $3,000; + billable expense $250 → planned revenue $3,250
Planned work cost = 90 × 20 = $1,800; + expense cost $200 → planned cost $2,000
If that expense were non-billable, planned revenue would stay $3,000 (nothing is billed) while planned cost would still be $2,000.
On a fixed-price project the planned cost is identical, but planned revenue would be the Budget recognized across the week by the project's method — not the $3,000 from the Allocation.
Related
Metrics glossary — the formulas behind Operating's numbers — Planned revenue, Planned cost, Planned expense in the glossary